How to use this concrete calculator
- Pick the shape. Choose the shape that matches your pour: slab, footing, post hole, column, wall, step, curb or one of the special shapes. For an L-shaped patio or a slab with a step-down, add a second section.
- Measure and enter. Type length and width in feet and the thickness in inches (or switch to meters and centimeters). Fractions and feet-inch entries like 12' 6" work.
- Set waste and bag size. Leave 10% waste for most flatwork. Pick the bag size you plan to buy, or compare all four.
- Add the extras. Tick gravel base or rebar if your project needs them, and enter local prices to see the total cost.
- Order. Use the rounded yard figure when calling a ready-mix plant, or copy the shopping list for a store run.
Works in your phone's browser, no app needed
Open this page on your phone, enter dimensions, and read yards and bags. Nothing to install; your numbers stay in the browser session.
How much concrete do I need?
Concrete is sold by volume, so every estimate comes down to one number: cubic yards. Multiply length by width by thickness with all three in feet, then divide by 27, because one cubic yard holds 27 cubic feet. A patio 12 ft long, 10 ft wide and 4 in thick is 12 × 10 × 0.333 = 40 ft³, which is 1.48 yd³. Add waste and round up to the next quarter yard and you would order 1.75 yd³.
The mistake we see most often is leaving thickness in inches. Four inches is a third of a foot, not four feet; enter it as inches in the calculator and it converts for you.
Measuring depth on uneven or sloped ground
Subgrade is rarely flat. Measure the form depth in at least four spots: near each corner and at the center. Use the average thickness in the calculator, or split the pour into two rectangles if one side is clearly deeper. On a slope, measure along the downhill edge and the uphill edge separately, then average. If the slope is steep, treat it as two slabs with different thicknesses instead of one average.
Irregular shapes: split into rectangles and circles
L-shaped patios, curved bump-outs, and cut corners are easier as simple parts. Draw the outline on paper, divide it into rectangles and quarter-circles, and add each part as its own section in the calculator. A round hot-tub pad beside a rectangle is one rectangle plus one round slab. Do not guess one big rectangle around the whole outline, because that overstates the volume.
Doing the math by hand
Three formulas cover most home pours. Slab: L × W × T in feet, then ÷ 27 for cubic yards. Round column: π × r² × H ÷ 27. Post hole: cylinder volume minus the post, then ÷ 27. For every shape, shortcuts, and unit checks, see the concrete formula guide.
Concrete formulas for every shape
| Shape | Formula (feet) | Example |
|---|---|---|
| Rectangle slab, footing, wall, beam | L × W × T ÷ 27 = yd³ | 20 × 12 × 0.333 ÷ 27 = 2.96 yd³ |
| Round slab or column | π × r² × H ÷ 27 | r 1 ft, H 4 ft → 0.47 yd³ |
| Hollow tube / ring (sonotube) | π × (R² − r²) × H ÷ 27 | R 1 ft, r 0.75 ft, H 3 ft → 0.15 yd³ |
| Post hole with post | (π r² × (depth − gravel) − post area × embed) ÷ 27 | see worked example |
| Triangle slab | ½ × base × height × T ÷ 27 | 10 × 8 × 0.333 ÷ 2 ÷ 27 = 0.49 yd³ |
| Sloped slab | L × W × (T1 + T2) ÷ 2 ÷ 27 | 10 × 10 × 0.417 ÷ 27 = 1.54 yd³ |
| Trapezoid curb/footing | (top + bottom) ÷ 2 × H × L ÷ 27 | existing example |
| Stairs | W × run × rise × (1+2+…+n) ÷ 27 | 4 × 0.917 × 0.583 × 6 ÷ 27 = 0.48 yd³ |
| Curb and gutter | (curb depth × curb height + gutter width × flag thickness) × L ÷ 27 | existing example |
In metric, multiply meters and skip the ÷ 27; the answer is already in m³. One m³ equals 1.308 yd³.

Bags at a glance
One cubic yard is about 45 bags of 80 lb mix at 0.60 ft³ per bag (QUIKRETE 1101). The tool above totals bags for your pour; for pallets, yields and brand tables, use the concrete bag calculator.
Bags or a ready-mix truck?
Under about one yard, bags often win on hassle. Above that, ready-mix is usually faster and about 45 × 80 lb bags per yard to lift by hand. Compare with your quotes on the concrete cost calculator and read when bags stop making sense on the bag page.
Typical thickness by project
| Project | Typical thickness |
|---|---|
| Sidewalk or patio | 4 in |
| Shed base | 4 in |
| Hot-tub pad | 4–6 in (check the tub maker's manual) |
| Driveway | 4–6 in (5–6 in for heavier vehicles) |
| Garage floor | 4–6 in |
| RV / heavy equipment pad | 6–8 in |
| Fence post footing | hole 3× post width, depth ⅓–½ of above-ground height plus 6 in gravel |
| Deck footing | follow local frost depth and code |
Your local building department has the final word on footings and anything structural.
Adding gravel under the slab
Most patios use about 4 in of compacted crushed stone; tick "Add gravel base" for cubic yards and tons. Depth, stone type, and tons are covered in gravel under a concrete slab.
Rebar and wire mesh
Rebar does not change how much concrete you need, but it does change how many sticks and ties you buy. For a residential slab the usual pattern is #3 or #4 bar on a grid 12 to 24 inches apart, held at mid-depth on plastic chairs so it is actually inside the slab. Enter bar size, spacing, edge cover and lap length and the calculator counts bars both ways, adds laps, converts to 20 ft sticks and estimates weight. Footings and walls designed by an engineer or required by code follow those drawings, not a rule of thumb.
| #3 | 0.376 |
| #4 | 0.668 |
| #5 | 1.043 |
| #6 | 1.502 |
Weight at a glance
Normal-weight concrete is about 150 lb/ft³, or roughly 4,050 lb/yd³. Change density in the tool or use the concrete weight calculator for pounds, tons, and kilograms from volume.
What does concrete cost?
Prices change by region, season and plant, so YardPour does not show a built-in price. Call two local ready-mix suppliers for their per-yard price, minimum load and short-load fee, and check the shelf price of the bag size you want. Put those numbers into the cost section and you get a complete total that reflects your town, not a national average.
How long does concrete take to cure?
Most mixes can be walked on after about a day, take light foot traffic and furniture after a few days, and handle cars after about a week, while full design strength is usually counted at 28 days. Keep the surface damp or covered for the first week, especially in hot, dry or windy weather, and don't let fresh concrete freeze. Fast-setting post mix sets far quicker; follow the bag.
Worked examples
12 × 20 ft patio, 4 in thick
- Thickness in feet: 4 ÷ 12 = 0.333 ft.
- Volume: 12 × 20 × 0.333 = 80 ft³.
- Cubic yards: 80 ÷ 27 = 2.96 yd³ net. With 10% waste, order 3.26 yd³, which the order sheet rounds to 3.5 yd³ at quarter-yard steps.
24 × 24 ft garage slab with a thickened edge
Slab: 24 × 24 × (4 ÷ 12) = 192 ft³ = 7.11 yd³. A thickened edge is extra concrete under the perimeter, not a second full slab. Perimeter is 96 ft. An edge 12 in wide and 8 in deeper than the slab is 96 × 1 × (8 ÷ 12) = 64 ft³ = 2.37 yd³. Add them, then add waste once.
Eight fence-post holes
Eight holes with a fence post subtracted: use the post-hole shape or the fence post calculator for each line post group.
Concrete steps: 3 steps, 4 ft wide
Rise 7 in, run 11 in. Each step is a block stacked on the one below, so the volume is width × run × rise × (1 + 2 + 3) = 12.83 ft³ = 0.48 yd³. With 10% waste that is 14.1 ft³: 24 bags of 80 lb.

Metric slab: 4 m × 3 m × 10 cm
4 × 3 × 0.10 = 1.2 m³, 1.32 m³ with 10% waste, which is 1.73 yd³ or 78 bags of 80 lb (2,200 lb is the 1 t mark; this job is well over two tonnes of dry mix — a short ready-mix load makes sense).
Mailbox post: one 10 in hole, 36 in deep, 4×4 post
6 in gravel, 30 in of post in concrete. Concrete is 1.15 ft³ after subtracting the post: 2 bags of 80 lb or 4 bags of 40 lb fast-setting. See the post hole shape.

Choosing a concrete mix
| Mix | Typical use | Notes |
|---|---|---|
| General purpose (about 2,500–3,000 psi) | Patios, walks, footings, steps | Good default for most home jobs |
| High strength (4,000 psi or more) | Driveways, garage floors, heavy-load pads | Common ask from ready-mix plants for flatwork that sees cars |
| Fast-setting | Fence posts, mailbox posts, quick repairs | Often poured dry into the hole and soaked; check the bag |
| Fiber-reinforced | Slabs where shrinkage cracks are a worry | Fibers help with surface cracking; they do not replace structural rebar |
| Ready-mix truck | Anything over about 1 yd³ | Tell the plant the strength, slump and any air entrainment for freeze-thaw areas |
Mix ratio by volume for site-mixed general concrete is commonly 1 part cement, 2 parts sand and 3 parts gravel; pre-blended bags already have this done for you.
Concrete estimator: from takeoff to order
Figuring concrete for a whole job means adding each rectangle, footing, or hole as its own section. The calculator totals volume, applies waste once, and gives one order number. Columns, block walls, and specialty shapes each have their own pages when you only need one shape.
A full concrete take off, worked
Concrete estimating for a DIY project or a small bid follows the same order every time: list every pour (slabs, footings, post holes, or a concrete fill for a trench or void), measure it, convert to volume, then decide what arrives by truck and what you mix from premix bags. Here is a backyard job estimated end to end.
| Item | Size | Math | Volume |
|---|---|---|---|
| Patio | 12 × 16 ft, 4 in | 192 × 4 ÷ 324 | 2.37 yd³ |
| Walkway | 4 × 20 ft, 4 in | 80 × 4 ÷ 324 | 0.99 yd³ |
| Pergola post holes | 6 holes, 10 in wide, 30 in deep | 6 × π × (5 ÷ 12)² × 2.5 | 8.18 ft³ (0.30 yd³) |
The patio and walkway total 3.36 yd³; with 5% waste that is 3.53 yd³, so one ready-mix order of 3.75 yd³ covers both pours. The post holes are small and often set on a different day, so they go on the bag list instead: 8.18 ft³ ÷ 0.60 ft³ per 80 lb bag = 13.6, so 14 bags before subtracting the posts (the post hole calculator does that subtraction). The base aggregate under the patio and walk is a separate line; the crushed concrete calculator handles it in yards and tons. If you are pricing this for a client, the estimation of concrete is the first line of the bid; forms, base, reinforcement, labor and finishing are separate lines.
Concrete conversion chart
These are exact unit conversions (and one planning density), handy when a plan, a supplier and a bag label use different units. The online calculator above is free and does the conversion for you; this chart is for checking a number by hand.
| From | To |
|---|---|
| 1 cubic yard (a 3 ft cube) | 27 ft³ = 0.765 m³ |
| 1 m³ | 1.308 yd³ = 35.31 ft³ |
| 1 ft³ | 1,728 in³ = 7.48 US gallons |
| 1 yd³ spread 4 in thick | 81 sq ft |
| 1 yd³ at 150 lb/ft³ (planning density) | 4,050 lb ≈ 2.0 short tons |
| 1 pallet (skid) of 80 lb QUIKRETE 1101 | 42 bags ≈ 25.2 ft³ ≈ 0.93 yd³ |
For concrete tonnage, multiply cubic yards by about 2.0 (or use the weight calculator with your mix density). For a round pour, the radius is half the diameter—entering the diameter as the radius is a fourfold overestimate.
Cement vs concrete
Cement is the gray powder that binds everything. Concrete is cement plus sand, gravel, and water. You pour concrete.
What this calculator does not do
- It estimates volume. It does not design footings, size rebar, or check local code.
- It does not price your job: prices you enter stay in your browser and are not sent anywhere.
Tips for an accurate estimate
- Measure in three places across a slab and use the average thickness, not the deepest point.
- Check forms are square by measuring both diagonals; they should match.
- Round up, never down. Running short mid-pour leaves a cold joint.
- Add a section for each thickened edge, step-down or footing that pours with the slab.
- For post holes, measure the hole you actually dug; augers drift wider than their rated size.
- Buy a couple of extra bags for small jobs; most stores take back unopened bags (check the store's policy).
Related field guides
- When you can drive on new concrete — walk, car and truck cure times.
- When you can drill into new concrete — 7-day and 28-day rules for anchors.
- How to pour a small concrete slab — forms, base, finish and joints.
- How to order ready-mix concrete — yards, tickets and truck day.
- Gravel under a concrete slab — depth, stone type and tons.
- How to set fence posts in concrete — hole sizes and bracing.
- Pouring concrete in cold weather — 40 °F rule and blankets.
- How to resurface concrete — when a thin overlay is enough.
- Why concrete calculators disagree — waste, yield and rounding.
Cite this page
YardPour Team. (November 17, 2026). Concrete Calculator. YardPour. https://yardpour.com/concrete-calculator/
Accessed October 11, 2026. Calculator inputs stay in your browser unless you use a share link.
Sources
- QUIKRETE Concrete Mix No. 1101 data sheet (40 / 50 / 60 / 80 lb yields)
- Portland Cement Association, Design and Control of Concrete Mixtures (overview)
- ACI 318-19, Building Code Requirements for Structural Concrete (ACI Bookstore)
- ACI 302.1R, Guide to Concrete Floor and Slab Construction (ACI)
- ACI 332, Residential Code Requirements for Structural Concrete (ACI)
- Portland Cement Association, Concrete technology and basics
- CRSI, Education and reinforcing steel resources
Checked October 11, 2026.