YardPour

Cubic yards to order

Concrete Yard Calculator

This concrete yard calculator is for cubic yards and truck orders: turn length, width, and depth into the yards you tell the ready-mix plant. Cubic yards = length × width × depth in feet ÷ 27. Add every pour as a section, choose your waste, and you get one number to order. It doesn't count bags or cost; for bags, rebar and a shopping list, use the main concrete calculator or this ready-mix calculator for yards only. Before you phone the plant, read how to order ready-mix concrete.

Updated Free · no sign-up · inputs stay in your browser

Pour dimensions

Section 1
11.23 yd³
ft
ft
in
Waste / overage
%
Default is 0%, so the net number is the true geometry. Many people add 5–10% for uneven subgrade, form bulge, and spillage.
$
Your local quote. We do not publish prices.

Concrete to order

1.23yd³

No waste added · 33.33 ft³

Net volume
1.235 yd³
Order volume
1.235 yd³
Cubic feet
33.33 ft³
Cubic meters
0.944 m³

Bags (rounded up after waste)

Bags needed by bag size
BagYield (ft³)Per yd³Bags
40 lb90112
50 lb7289
60 lb6075
80 lb4556

Default yields: QUIKRETE No. 1101 data sheet. Edit them to match your bag.

V = L × W × T yd³ = ft³ ÷ 27 · order = net × (1 + waste) bags = ⌈order ft³ ÷ yield⌉

Most plants sell in quarter- or half-yard steps and have a minimum load. Round this order up to your supplier's increment before you call.

Show the math
  1. Slab: 33.33 ft³
  2. Net volume: 33.33 ft³
  3. Order volume: 33.33 × (1 + 0%) = 33.33 ft³ = 1.235 yd³
  4. 80 lb bags: 33.33 ÷ 0.6 = 55.56, rounded up to 56

Need delivery, short-load fees, tax, or a bags-vs-truck comparison? Use the concrete cost calculator.

One cubic yard is 3 ft by 3 ft by 3 ft, or 27 cubic feet

How to figure concrete yardage

To figure yards of concrete from a flat slab, multiply square feet by thickness in inches and divide by 324. A 10 × 10 ft pad at 4 inches is 100 × 4 ÷ 324 = 1.23 yd³ before waste. For stairs, footings, or several pieces, add each part on the concrete calculator.

How big is a yard of concrete?

A cubic yard is a cube 3 ft on each side, or 27 cubic feet. At 4 in thick it covers about 81 sq ft; at 6 in, about 54 sq ft. Every yard calculation ends with ÷ 27.

How concrete is measured for an order

Ready-mix plants batch and bill in cubic yards (or m³). You give them order yards after waste and rounding—net geometry is what you measure; order volume is what the truck brings.

yd³ = L(ft) × W(ft) × D(ft) ÷ 27 yd³ = sq ft × D(in) ÷ 324 4 in slab: yd³ ≈ sq ft ÷ 81

The ÷ 81 shortcut comes from 324 ÷ 4 = 81. It is exact at 4 inches and wrong at any other depth. At 6 inches the divisor is 54.

Worked example: 12 × 20 ft driveway section, 5 in thick

  1. Area: 12 × 20 = 240 sq ft.
  2. Cubic yards: 240 × 5 ÷ 324 = 3.70 yd³ net.
  3. With 5% waste: 3.70 × 1.05 = 3.89 yd³.
  4. Rounded up to the next ¼ yard: order 4.0 yd³.

After the pour, wait for cure before car traffic. Our drive-on timeline guide walks through walk, car, and truck timing.

How much does a yard of concrete cover?

Coverage depends only on thickness. Coverage (sq ft) = 324 ÷ thickness (in).

ThicknessSq ft per cubic yard
3.5 in92.6
4 in81.0
5 in64.8
6 in54.0
8 in40.5
12 in27.0

This is coverage, not price. For cost per yard with your own quote, use the concrete cost calculator.

Download the concrete order worksheet (PDF) — free to use with a link to YardPour.

How to estimate concrete yards for an order

  1. Measure each part of the pour separately: slab, thickened edges, footings, piers.
  2. Add them as sections above. The total updates as you go.
  3. Decide on waste. 0% shows the true geometry. 5–10% covers uneven subgrade and spillage .
  4. Ask your supplier how they sell partial yards (¼ or ½ yd³ steps are common), and what the truck minimum is .
  5. Order a little over, not under. A short load costs more than a few spare cubic feet.

How to figure out yards of concrete, step by step

Figuring cubic yards of concrete takes four steps: measure in feet, multiply length × width × depth, divide by 27, then add waste and round up to the plant's increment. The same steps work whether you call it finding, figuring or determining yards—only the shape changes.

  1. Measure. Tape the length and width at two or three places and use the average. Measure depth from the top of the form board to the compacted base, not to the dirt you have not dug yet.
  2. Convert inches to feet. 4 in = 0.333 ft, 5 in = 0.417 ft, 6 in = 0.5 ft. Skipping this step is the most common way to order 12 times too much.
  3. Multiply and divide by 27. Cubic feet ÷ 27 = cubic yards.
  4. Add waste and round. Multiply by 1.05 to 1.10 and round up to the next ¼ or ½ yard your supplier sells.

Worked example: L-shaped patio, 4 in thick

  1. Split the L into two rectangles: 16 × 12 ft and 8 × 6 ft.
  2. Areas: 192 sq ft + 48 sq ft = 240 sq ft.
  3. Cubic feet: 240 × 0.333 = 80 ft³.
  4. Cubic yards: 80 ÷ 27 = 2.96 yd³ net.
  5. With 8% waste: 3.20 yd³. Order 3.25 yd³.

How far will a yard of concrete go?

One yard goes about 81 sq ft at 4 inches, 54 sq ft at 6 inches, and 162 sq ft at a 2 inch overlay. Bigger orders scale the same way: 15 yards of concrete cover about 1,215 sq ft at 4 inches or 810 sq ft at 6 inches, and 16 yards cover about 1,296 sq ft or 864 sq ft. Those are net figures—hold back a few percent for an uneven base.

How many pounds of concrete are in a yard?

Roughly 3,800 to 4,050 lb. A yard is 27 ft³; at the 140 lb/ft³ that QUIKRETE lists for its 1101 mix that is 3,780 lb, and at the common 150 lb/ft³ planning figure it is 4,050 lb. A ready-mix truck carrying several yards is therefore hauling many tons, which is why plants ask about access and soft ground. Weight for any volume is on the concrete weight calculator.

How concrete is measured and sold

Ready-mix is measured and sold by the cubic yard of plastic (fresh) concrete, batched by weight at the plant to hit that volume. Bagged mix is sold by weight, with the yield in cubic feet printed on the bag (0.60 ft³ for an 80 lb bag of QUIKRETE 1101). So yards are the unit for a truck order and cubic feet are the unit for bags; the bag calculator converts one to the other.

Yards or bags?

Under about one yard, bags may be simpler; above that, call the plant with order yards from this page. Bag counts by size are on the concrete bag calculator.

Sources

Checked October 11, 2026.

Frequently asked questions

How many yards of concrete do I need?

Multiply length × width × depth in feet and divide by 27, or for a flat slab use square feet × thickness in inches ÷ 324. A 10 × 10 ft pad at 4 inches is 100 × 4 ÷ 324 = 1.23 yd³ before waste.

How much does a yard of concrete cover?

One cubic yard covers about 81 square feet at 4 inches thick, 65 square feet at 5 inches, and 54 square feet at 6 inches. Coverage = 324 ÷ thickness in inches.

How do I figure yards of concrete?

Multiply length × width × depth in feet to get cubic feet, then divide by 27. For a slab with depth in inches, use square feet × inches ÷ 324.

Should I round up my concrete order?

Yes. Running short means a second delivery or a cold joint. Many people add 5 to 10 percent and round up to the increment the supplier sells, often a quarter or half yard.

How many cubic feet are in a yard of concrete?

27. A cubic yard is 3 feet × 3 feet × 3 feet. To convert cubic feet to cubic yards, divide by 27.

How do I figure out concrete yardage for a round slab?

Find the area with π × radius², multiply by thickness in feet, and divide by 27. A 10 ft round pad at 4 inches is 3.1416 × 5² × 0.333 ÷ 27 = 0.97 yd³ before waste.