How to figure concrete for a slab
- Measure the length and width in feet. For an L-shaped slab, split it into two rectangles and add both as separate slabs.
- Pick a thickness in inches. Measure the form depth in a few spots, because subgrade is rarely perfectly flat.
- Square feet = length × width.
- Cubic yards = square feet × thickness (in) ÷ 324.
- Add waste if you want a margin, then round up to how your supplier sells.
Why 324? A cubic yard is 27 cubic feet, and a foot is 12 inches, so 27 × 12 = 324. The ÷ 81 shortcut only works at exactly 4 inches. The formula guide walks through the algebra.
Worked example: 10 × 10 ft slab, 4 in thick
- Area: 10 × 10 = 100 sq ft.
- Cubic yards: 100 × 4 ÷ 324 = 1.23 yd³.
- Cubic feet: 1.23 × 27 = 33.33 ft³.
- 80 lb bags: 33.33 ÷ 0.60 = 55.6, which rounds up to 56 bags.
Common slab sizes at a glance
Net volume, no waste, 80 lb bags at 0.60 ft³ each . Yards = sq ft × thickness (in) ÷ 324.
| Slab | 4 in | 5 in | 6 in |
|---|---|---|---|
| 4 × 4 ft | 0.20 yd³ · 9 bags | 0.25 yd³ · 12 bags | 0.30 yd³ · 14 bags |
| 8 × 8 ft | 0.79 yd³ · 36 bags | 0.99 yd³ · 45 bags | 1.19 yd³ · 54 bags |
| 10 × 10 ft | 1.23 yd³ · 56 bags | 1.54 yd³ · 70 bags | 1.85 yd³ · 84 bags |
| 10 × 12 ft | 1.48 yd³ · 67 bags | 1.85 yd³ · 84 bags | 2.22 yd³ · 100 bags |
| 12 × 12 ft | 1.78 yd³ · 80 bags | 2.22 yd³ · 100 bags | 2.67 yd³ · 120 bags |
| 20 × 20 ft | 4.94 yd³ · 223 bags | 6.17 yd³ · 278 bags | 7.41 yd³ · 334 bags |
| 20 × 30 ft | 7.41 yd³ · 334 bags | 9.26 yd³ · 417 bags | 11.11 yd³ · 500 bags |
| 30 × 40 ft | 14.81 yd³ · 667 bags | 18.52 yd³ · 834 bags | 22.22 yd³ · 1000 bags |
| 24 × 24 ft | 7.11 yd³ · 320 bags | 8.89 yd³ · 400 bags | 10.67 yd³ · 480 bags |
At these sizes a ready-mix truck usually beats bags. Compare both with your own prices in the concrete cost calculator.
Typical slab thickness
| Use | Often cited |
|---|---|
| Sidewalk, patio, shed pad | 4 in |
| Garage floor / light pad | 4–6 in |
| Vehicle driveway | 4–6 in — use the driveway calculator |
| Slab-on-ground minimum (IRC) | 3.5 in, as cited by some pages |
These are typical figures, not code. Heavy vehicles, poor soil, or frost may call for more. Check your plans and your local building department. Thickness and mix strength go together: see what psi concrete to order for a driveway, and check curing times in our drive-on timeline guide.
Monolithic slab vs slab on grade
A monolithic slab pours footing and floor in one piece, so volume is the flat slab plus any thickened edge or perimeter strip. A slab on grade is the floor only, usually on a gravel base. Add thickened edges as their own section in the main calculator when they are not in your rectangle.
Slab shapes beyond rectangles
Round hot-tub pads, half-circle bump-outs, and shed pads use the round shape above. Split L-shaped patios into two rectangles and add both sections.
Sloped slabs and ramps
For a ramp or driveway section with different thickness at each end, use the sloped slab shape on the concrete calculator and enter thickness at the high and low edges.
Slab foundations, basement floors and garage floors
For a slab foundation, add the flat floor and the thickened perimeter as separate pieces; for a basement or garage floor inside existing walls, the floor alone is the whole order. Footing width, edge depth and reinforcement come from your plans or building department—this page only turns those sizes into concrete.
Worked example: 20 × 30 ft monolithic slab foundation
- Floor: 20 × 30 = 600 sq ft at 4 in → 600 × 4 ÷ 324 = 7.41 yd³.
- Perimeter edge: 100 ft long, 12 in wide, 8 in deeper than the floor → 100 × 1 × 0.667 = 66.7 ft³.
- Corners are counted twice along a perimeter, so subtract 4 × (1 × 1 × 0.667) = 2.7 ft³ → 64.0 ft³ = 2.37 yd³.
- Total: 7.41 + 2.37 = 9.78 yd³. With 5% waste, 10.27 yd³; order 10.5 yd³.
Worked example: 30 × 40 ft basement floor, 4 in
- Area: 1,200 sq ft.
- Volume: 1,200 × 4 ÷ 324 = 14.81 yd³ net.
- Basement floors are often poured over a gravel or crushed-stone layer that is rarely perfectly flat; with 8% waste the order is 16.0 yd³.
- Pump or chute access matters more than volume here—tell the plant it is a basement pour when you order.
From square footage to yards
If you already know the square footage, you can skip length and width: cubic yards = square feet × thickness (in) ÷ 324. So 1,200 square feet at 4 inches is about 14.8 yards, and the same area at 6 inches is 22.2 yards.
| Area | 4 in | 5 in | 6 in |
|---|---|---|---|
| 100 sq ft | 1.23 yd³ | 1.54 yd³ | 1.85 yd³ |
| 200 sq ft | 2.47 yd³ | 3.09 yd³ | 3.70 yd³ |
| 400 sq ft | 4.94 yd³ | 6.17 yd³ | 7.41 yd³ |
| 600 sq ft | 7.41 yd³ | 9.26 yd³ | 11.11 yd³ |
| 800 sq ft | 9.88 yd³ | 12.35 yd³ | 14.81 yd³ |
| 1,000 sq ft | 12.35 yd³ | 15.43 yd³ | 18.52 yd³ |
| 1,200 sq ft | 14.81 yd³ | 18.52 yd³ | 22.22 yd³ |
| 1,500 sq ft | 18.52 yd³ | 23.15 yd³ | 27.78 yd³ |
Triangle and circular slabs
A triangle is half of a rectangle: area = ½ × base × height. A corner patio with a 12 ft base and 9 ft height is 54 sq ft; at 4 in that is 54 × 4 ÷ 324 = 0.67 yd³. A circular slab uses area = π × radius²: a 12 ft diameter hot-tub pad (6 ft radius) is 113.1 sq ft, or 1.40 yd³ at 4 in. Mixed shapes are easiest as separate sections in the main concrete calculator.
Gravel base under a concrete slab
Tick the gravel panel for base cubic yards and approximate tons from your slab area. Depth and stone type: gravel under a concrete slab.
Worked example: 10 × 10 ft slab with a 4 in gravel base
- Slab area: 10 × 10 = 100 sq ft.
- Gravel depth: 4 in = 4 ÷ 12 = 0.333 ft.
- Gravel volume: 100 × 0.333 = 33.33 ft³ = 1.23 yd³ loose.
- At 1.4 tons per yd³ (confirm with your supplier): about 1.7 tons.
Rebar grid for a slab
Rebar does not change concrete volume in a meaningful way for ordering, but it does change what you buy. Open the rebar panel for bar count and weight, or see rebar vs wire mesh for a concrete slab to choose mesh instead of tied bar.
A reinforced concrete slab needs the same concrete volume as a plain one; slab reinforcement only adds bars or mesh, chairs and tie wire to the shopping list. Bar size and spacing should come from your plans.
Concrete slab estimator tips
- Thickened edges and footings under the slab are extra volume. Add them as their own section in the main concrete calculator.
- Low spots in the subgrade eat concrete. A 4 in slab poured on a base that dips to 4.5 in uses 12.5% more in that area.
- For bags only, the concrete bag calculator shows 40, 50, 60, and 80 lb counts side by side.
Related guides
- Concrete vs Asphalt Driveway: which lasts longer and how to estimate concrete.
- Finishing an existing slab? Read how to paint a concrete patio.
Sources
- QUIKRETE Concrete Mix No. 1101 data sheet (40 / 50 / 60 / 80 lb yields)
- Portland Cement Association, Design and Control of Concrete Mixtures (overview)
Checked October 11, 2026.